Analisis Produktivitas Alat Berat pada Pekerjaan Timbunan Kembali DPT Kiri Intake Kanan Proyek Bendungan Karangnongko
Analisis Produktivitas Alat Berat dalam Pekerjaan Timbunan Kembali DPT Kiri Intake Kanan pada Proyek Pembangunan Bendungan Karangnongko
Keywords:
heavy equipment, backfill, effectiveness, dam, construction managementAbstract
Backfill work DPT on retaining walls is a critical stage in dam construction as it affects structural stability. This study aims to analyze heavy equipment productivity and time effectiveness in the backfill work of the left retaining wall at the right intake of the Karangnongko Dam project, using a quantitative method through field observation and cycle time analysis.
The results show that the Kobelco SK200-10 excavator and Komatsu D21P-7E bulldozer achieved productivities of 56.73 m³/hour and 56 m³/hour, respectively, with 100% time effectiveness, indicating alignment between planning and execution. The Mitsubishi Fuso dump truck demonstrated higher efficiency, achieving 133% time effectiveness by completing work faster than planned. In contrast, the LiuGong 6611E vibratory roller exhibited high productivity but low effectiveness (-133.3%) due to excessive idle time. Overall, the study highlights that optimal equipment performance depends on proper synchronization and operational management. Efficient utilization of certain equipment can compensate for inefficiencies in others, ensuring balanced project time and cost performance.
Downloads
References
Indonesia, M. P. umm D. P. R. R. (2022). Peraturan Menteri PUPR No 1 Tahun 2022 Tentang Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum Dan Perumahan Rakyat. Menteri Pekerjaan Umum Dan Perumahan Rakyat Republik Indonesia Nomor 1 Tahun 2022, 95–140.
Lo, J., & Nuh, S. M. (2021). Analisis Metode Pelaksanaan Konstruksi Pada Proyek Breakwater Kabupaten Mempawah. 234–221.
Ramadhan, E. P. (2024). Produktivitas Alat Berat Dump Truck Pada Pekerjaan Galian Dan Urugan Tanah Dengan Alat Pemuat Backhoe Pc 78 Proyek Tahap 3 …. Jurnal Vokasi Teknik Sipil, 2(2), 1–6. https://ejournal.unesa.ac.id/index.php/viteks/article/view/62099
Seftiana Putri, K., & Soebandono, B. (2024). Produktivitas Alat Berat pada Pekerjaan Galian dan Timbunan Embung IKN Nusantara. Bulletin of Civil Engineering, 4(2), 55–60. https://doi.org/10.18196/bce.v4i2.25852
Setiawati, D. N. (2013). Analisis Produktivitas Alat Berat pada Proyek Pembangunan Pabrik Krakatau Posco Zone IV di Cilegon. Jurnal Konstruksia, 4, 91–103.
Supit, D. D. (2020). ANALISA PRODUKTIVITAS DAN EFISENSI ALAT BERAT UNTUK PEKERJAAN TANAH, DAN PEKERJAAN PERKERASAN BERBUTIR (Studi Kasus : Proyek Rehabilitasi Ring Road II – Paniki). Journal Dynamic Saint, (1), 906–917. journals.ukitoraja.ac.id
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Fajar Setiawan, Nadya Roselin Wahyudi

This work is licensed under a Creative Commons Attribution 4.0 International License.